Introduction
Waterlines comprise well over half of a water utility’s
built infrastructure. Most of our waterline infrastructure
is over forty years old and, with age, leaks and breaks
increase, causing concern about water quality, system
dependability, and public risk. Yet, waterline restoration
must compete for limited dollars within water utility
budgets. Using “break” history criterion to replace
waterlines typically results in replacement of some
deteriorated waterline segments as well as the replacement
of many waterline segments that have substantial remaining
useful life. In other words, this single criterion is not
cost efficient. More waterlines can be restored within a
given budget through the use of a structural condition
assessment technology, such as Remote Field Technology
(RFT).
This paper describes the City of Calgary’s use of RFT to
establish an asset management approach to waterline
restoration. The approach enables the city to establish
priorities that enhance optimum utilization of budgeted
funds. The technology is described as it is used in the
field. RFT results have been confirmed by visual examination
of samples of excavated cast-iron and ductile-iron pipe. The
city’s use of RFT data to pro-actively restore waterlines is
presented, along with an analysis of resulting avoided
costs.
Waterline Prioritization
“Break” history, the number of breaks over a given length of
line in an established time period, is a common method of
prioritizing waterlines for replacement or restoration. This
method of line selection is not always cost-effective as it
usually results in wholesale replacement of a length of
waterline without knowledge as to the remaining useful life
of the entire line. Waterline breaks typically can be traced
to corrosion, which does not occur consistently, nor can it
be predicted over a length of line. Severe corrosion in a
few areas of a waterline does not mean that there is
corrosion in other areas of the same waterline. Thus,
replacement of waterlines based on “break” history results
in the replacement of miles of
waterline of which the condition is not known. This practice
may be considered imprudent when funding is limited and
needs are great.
The pro-active waterline distribution manager requires more
knowledge as to the condition of the waterlines. Such
knowledge may be derived from the collection of data
regarding soils characteristics, pipe materials, types and
location of service connections, visual inspection of
exhumed pipe, and operating conditions. Various combinations
of this data combined with “break” history may suggest
trends in corrosion rates, allowing the manager to
prioritize waterline for replacement in a more effective
manner.
However, even with improved prioritization tools, the
distribution manager has only gained a better focus as to
waterline replacement needs. The additional data still fails
to provide detailed knowledge as to the condition of the
waterlines. A final step is necessary to complete an
accurate condition assessment and, thus, allow for
optimization of limited financial resources. RFT is the tool
used by the City of Calgary.
Remote Field Technology
Remote Field Technology has been used in oil well field and
industrial boiler inspections for decades. Only recently has
a tool been developed and patented for use in the water
utility industry. For waterline inspection, the RFT
circuitry is imbedded in sealed modules that are connected
to each other to form a flexible mechanical probe (the RFT
tool). The modules, made of stainless steel, are connected
to a host computer via a 3,000-foot cable. The modules are
connected to each other by U-joints, enabling the entire
device to traverse bends and tee paths within the pipe. The
tool can be easily inserted into a water pipe at a fire
hydrant or other convenient access point. Once inside the
pipe, the tool is propelled through the pipe either by water
pressure or by pulling the tool through a dry line. Figure 1
is a diagram of the tool.
Waterline inspection by Remote Field Technology results in
the ability to locate and measure areas of corrosion and
other defects. RFT measures the wall thickness of a pipe by
passing an electromagnetic signal through the pipe wall.
Changes in the signal are analyzed, resulting in
identification of pipe defects. By passing a low frequency
current through an exciter coil, the coil is able to
generate and emit electromagnetic fields. The
electromagnetic field attenuates or weakens with distance
and shifts in phase as it travels away from the exciter
coil. Two distinct coupling paths exist between the exciter
and the detector coils: the direct path, which is down the
inside of the pipe; and the indirect path, through the pipe
wall near the exciter, down the outside of the pipe, and
then back through the pipe wall near the detector. The RFT
technique is centered on the electromagnetic field that
follows the indirect path. Figure 2 is a diagram of the RFT
technology.
By the time the field reaches the detector coil, the field
from the indirect route is greater than that from the direct
one, thus dominating the remote field. The attenuation and
phase delay of the electromagnetic signal that follows the
indirect path is sensitive to changes in wall thickness,
allowing corrosion pits and wall thinning to be detected.
The tool records data only when moving. The tool is designed
to take two readings of the same stretch of pipe: the first,
when the tool is initially propelled through the pipe; and
the second, when the tool is being retrieved. Readings are
amplified, filtered and digitized for transmission to the
above ground computer. One data set is obtained every 1.5 mm
of travel. The computer then gathers, processes, and stores
data for analysis. The data analysis results in a condition
assessment report, detailing the condition of each pipe
segment.
City of Calgary Approach
Validating RFT During a seven-year period (1993-1997), the
City of Calgary undertook an aggressive study to examine the
physical condition of water mains and identify the factors
that affect the corrosion process. The city contracted with
Hydroscope Canada the developer of a proprietary RFT tool
for waterline condition assessment. The accuracy of the
Hydroscope readings was verified via comparison to actual
pit depths measured on sample pipes that were later exhumed
and replaced. Results of this work were presented at length
at the AWWA Infrastructure Conference in 2001 [Kozhushner,
2001] and will be summarized below.
A few mains condition-assessed by Hydroscope were selected
for accuracy verification. This included mains that had
either high failure records or were practically without
failure. These were condition-assessed (Hydroscoped) and
samples recovered for examination, to verify Hydroscope
accuracy on a full spectrum of pipes; the total research
included every pipe material in all conditions, from the
worst to the best.
The pipe recovery sample size for a given job was generally
just over 100m; several samples were performed each year for
a total of nearly 2000m of pipe. A great deal of data about
these pipe sections and the soil in which they were bedded
was collected. For Hydroscope accuracy verification, the
pipe sections were laid out in a field in duplication of
their original order, and sandblasted (see Figure 4) to
reveal all of the corrosion pits and holes normally filled
with graphite plugs.
The pits were all recorded as part of the research effort to
connect corrosion with other factors such as soil chlorides,
sulphates and redox potentials; and correlated to Hydroscope
data: the three deepest pits on any given pipe-length of
main.
A system for categorizing the Hydroscope pit-depth findings
versus the visual measurement was developed. A set of four
"bins" was selected, matching the interests of the engineer
evaluating the pipe:
1. Through-holes and pits leaving under 20% wall remaining
thickness (W.R.T.)
2. Pits leaving between 20% & 40% W.R.T.
3. Pits leaving between 40% & 65% W.R.T.
4. Pits leaving over 65% W.R.T.
Each Hydroscope pit datum was compared to the appropriate
pit in the actual pipe. Results of the comparison of visual
measurement to Hydroscope findings are summarized in the
graphs below (Figure 6). All graphs are for the data
collected in 1999, which showed higher accuracy from the
Hydroscope process than 1998, indicating dramatic
improvement in the data interpretation - partly due to
collaboration between Calgary and Hydroscope.
It must be noted that visual measurement data can vary from
Hydroscope condition assessment data due to various factors.
One such factor is the reliability of the Hydroscope
technology, which is the purpose of the analysis. However,
variance can also be the result of tight clustering of pits
that are measured by Hydroscope as a single defect, the
existence of
graphitization that may not have been removed by
sandblasting, and interior wall defects. Each of these
variance factors can distort the comparison efforts. In all
of these cases, the volume of metal missing at any location
is actually detected better by the Hydroscope than by
pit-depth measurement. Therefore, the results of the
comparisons could only be favorably enhanced if these
conditions were known.
In summary of the comparative analysis, the City of Calgary
found:
• The Hydroscope pit depth data are within 20% W.R.T. of the
visually measured pit 95% of the time.
• The accuracy on the most important data for the evaluator
- through holes and very deep pits - is extremely high, with
nearly 90% of through-holes and deep pits being correct
calls.
• With the variances that can be expected between Hydroscope
analysis and visual measurement, the accuracy and
reliability of Hydroscoping is considered highly acceptable.
Practical Use of RFT
Based on Calgary’s analysis, Hydroscope evaluations of cast
iron
mains are used with confidence, not only to make
replace/defer
decisions on main replacement, but on decisions to replace
only short
segments of main. Calgary has reduced main replacements from
300m to 80m and even 60m, based on Hydroscope assessments
that
showed only 60m of the main to have severe pitting.
The map presented as Figure 7 provides an excellent overview
and
dramatic example of a water utility’s ability to control
main replacement costs with RFT. The project considered by
the City of Calgary was the
replacement of the waterline on the 4600 and 4700 blocks of
Montalban Drive NW. The water utility had recorded nine main
breaks on the 4700 block, while the 4600 block had no
breaks. The typical main-replacement program would have
called for the replacement of the waterline on both blocks,
due to the assumption that both had the same pipe
characteristics
(circa 1960, CI 6”) and the same soil characteristics and
resistivity. With such common characteristics, it might be
assumed that the 4600 block waterline would have similar
corrosion pits and a high probability of failure in the
future. However, Hydroscope data showed, unmistakably, that
this was not the case. The absence of failures on the 4600
block was not due to soil pressure delaying the “popping” of
holes, but to the lack of through-holes at all. One-third of
the waterline that would have been replaced
was not replaced at all, thus saving the City nearly
one-third of the project cost.
Calgary uses the “Hydroscope depth” for every pit to make
critical planning decisions. To that end, all Hydroscope
data are entered into the utility's GIS database so that the
corrosion profile for any Hydroscoped main can be brought up
as part of the map, or on a special "Infrastructure Viewer"
Java applet. This viewer shows Hydroscope data as a graph
with
distance along the main as the x-axis and wall thickness as
the y-axis, and each pit shown as a “mine shaft”, a black
vertical line from the top of the graph (outer wall) toward
the bottom of the graph (inner wall).
Five shades of blue are used in the background as a visual
reference to indicate the points of 100%, 80%, 60%, 40%,
20%, and 0% wall remaining. The above graphic (Figure 8) is
a view of the 4600 block of Montalban NW. It indicates only
four pits that have less than 40%
wall remaining, being the result of some 40 years of
corrosion. Some 35 remaining years of useful life may be
expected before the break-rate becomes intolerable. The
results for the 4700 block (Figure 9) were sharply
different. The profile shows a large number of throughholes
waiting to "pop", in addition to the nine breaks already
sustained. An equally large number of deep pits (20% wall
remaining) would follow in a few years. Note that the
infrastructure Viewer now shows the main at that location to
be "PVC 150 2000", the CI having been immediately replaced
in the following construction season.
In this example, at least 300m of replacement were deferred
at a savings in excess of roughly $200,000 Cdn.
Using Hydroscope and RFT in Progressive Program
Calgary's approach to ongoing use of Hydroscope and RFT
targets four critical uses for the technology:
1. Providing certainty in decision-making for "controversial
cases", such as mains with little prior history of failure
that would indicate need for replacement, but which have a
"golden opportunity" available at the time. An example is a
major downtown street with construction of a large
convention center that required a street closure and repairs
to the Centre Street Bridge. This project closed the traffic
bottleneck of Centre Street itself for the first time in 30
years. Before the availability of Hydroscope, both mains in
the street would have been routinely replaced since "that
opportunity won't come by for decades". However after
Hydroscoping both mains, it was determined that replacement
would not be necessary for several decades. Thus, the city
saved substantial replacement costs.
2. Additional decision-information for immediate replacement
decisions, which is the bulk of Calgary’s Hydroscope
program. About half of Calgary's replacement program each
year consists of mains that the city opts to replace based
solely upon failure records. The remainder of the program is
subjected to Hydroscope condition assessment. This allows
selection of certain mains from a prioritized candidate
pool. Using Hydroscope, the city makes spot restoration or
replacement decisions by identifying the location and extent
of existing through-holes or deep pits, and avoids wholesale
waterline replacement.
3. "Benchmarking" of the thick-wall cast iron system.
Previous research, including the first Hydroscope
experiments, shows that the consistency of deterioration
from one block of pipe to the next increases with wall
thickness. The thickest-walled pipe in the system, the
pit-cast iron pipe installed prior to 1955, is very
consistent in condition in adjacent blocks
of similar soil type and install date. A portion of the
city’s Hydroscope project from 1999 to 2002 established a
benchmark for mains of specific vintage and soil type. The
city Hydroscoped approximately 10% of the 500km inventory of
thick-wall cast iron mains with the intent of predicting the
lifecycle of the remaining 90%, using the "benchmark" mains
as a prioritization model.
4. Rehabilitation and life extension decision-making. The
term replacement" has been used throughout this paper, as it
is the most expensive waterline asset management option.
Waterline rehabilitation or restoration is, most often, a
more cost-effective solution. One such rehabilitation
technique used by Calgary is with cathodic protection
anodes, rather than total replacement. Again, the Hydroscope
is of definitive value in this program, as anode retrofit is
only appropriate to ductile iron mains that have significant
but not yet "fatal" corrosion levels -preferably almost no
pits of less than 50% W.R.T. A decision to use anode
retrofit for a main rather than replacement avoids about 75%
of the
construction cost.
While easy to calculate for one job, the savings resulting
from use of the Hydroscope are more difficult to assess for
the overall program. Merely counting up all the cases where
the Hydroscope data deferred a replacement is simplistic,
since Hydroscope data also have caused replacements to be
selected that would have been missed without it - yet
obviously it would be wrong to regard those cases as a
"cost" incurred from Hydroscoping. Those cases, too, are an
asset to the utility, since repairs and bad service to
customers are avoided by the replacement.
On the balance, the Calgary engineers regard the Hydroscope
RFT as a tool that increases the accuracy of the city’s main
replacement/rehabilitation selections from an 80% efficiency
rate
to over 90%, better than halving the error rate. For
corrosion-related replacement decisions, the main selection
accuracy is now, effectively, 100%. Since few utilities
check the accuracy of their existing selection techniques by
a sustained program of pipe recovery and sandblasting, it is
possible for them to presume every replacement job a
success. However, the early returns from Calgary's pipe
recovery work in the mid-1990's showed that about one main
in five then selected did not have to be replaced. From a
main replacement program of some $10 million Cdn. per annum,
about $2 million were being wasted. That waste is now
confined to mains that are selected without benefit of
Hydroscoping.
It is estimated that the City of Calgary has experienced an
approximate 100% payback on Hydroscope condition assessment
fees. The city estimates over $1 million in replacement
savings annually from the use of RFT, while the annual cost
of condition assessment is approximately $600,000. The
current $10 million annual budget for main replacement in
Calgary represents a significant reduction from the early
1990's, when it peaked at $17 million. It had been expected
that the budget would have to rise again as the rate base
grew to permit it. Partly because of Hydroscope technology,
however, it is now expected that the budget can remain level
and, indeed, be further reduced in the future, as the
cumulative effects of the more-accurate replacement program
are felt.
Conclusion
In order to reliably provide high quality water, waterline
asset managers must collect reliable data about the
condition and external influencers of waterlines. Although
“break” history combined with external data (such as soils
characteristics) may be used to prioritize waterlines for
replacement or restoration, knowing the actual condition of
the waterline is
critical to achieving optimum success with limited budgets.
Using RFT technology for waterline condition assessment
enables selective replacement and renewal. The City of
Calgary, working in collaboration with Hydroscope, has
gained significant cost effectiveness in its waterline asset
management program. Using RFT to determine actual waterline
condition, the City of Calgary has created efficiencies that
eliminate the use of scarce funding on unnecessary waterline
replacement. Further, the technology has resulted in the
prescription of repairs in instances where waterlines were
thought to be in good useful condition. The City of Calgary
has demonstrated that the application of RFT technology
significantly improves efficiency in waterline asset
management.